As with many live operational environments, this project required a thoughtful and flexible approach from the outset. Initial scoping identified gaps in site information, requiring additional discovery before further design could be carried out.
Due to the site’s proximity to a road and flight path, a glint and glare assessment was essential to ensure safety and compliance. The electrical infrastructure, dating back to the 1990s, posed integration hurdles, especially with limited spares and documentation. With backup generators in use, there were valid concerns about back-feeding and equipment protection.